Kaskia Wellbeing Block

Discover the Kaskia Wellbeing Block


Located in the heart of Turku, the Kaskia Wellbeing Block combines modern housing, care services, and shared spaces to create a safe and welcoming community. Follow the construction progress on our website and see how the neighbourhood is taking shape.

General working hours for tasks causing noise and vibration

(according to the City of Turku decision of 27 October 2025, valid until 30 June 2026)

  • Construction and demolition work: weekdays 7:00–18:00

  • Drilling, blasting and piling: weekdays 8:00–18:00

  • Concrete crushing: weekdays 9:00–17:00

  • Indoor demolition work (chipping): weekdays 7:00–20:00, up to two Saturdays per month 9:00–16:00. (During school summer holidays: weekdays 9:00–18:00)

  • No work is carried out on public holidays or equivalent days.


To reduce noise, vibration and dust, the site uses noise barriers, vibration monitoring and dust control measures.

About the project

The Kaskia Wellbeing Block is being developed to meet future housing, care and community living needs in the heart of Turku.

It will combine homes, wellbeing services and shared spaces – creating a natural meeting place for everyday life.

The project is being developed by Stiftelsen Eschnerska Frilasarettet, a Turku-based foundation, in collaboration with C.G. Sundell’s Foundation.

Construction began in 2025, with the first buildings scheduled for completion in 2027.

Latest updates

Foundation works progress – construction enters the next phase

Construction site update for weeks 19–20

The Kaskia wellbeing block construction site has entered a phase where foundation works, structural construction and renovation of existing buildings are progressing in parallel.

– Several work phases are ongoing simultaneously, which is typical for a project of this nature. The work is progressing according to plan, says site manager Matti Koivu from Lujatalo.

In the parking facility area, foundation works have begun on the Sirkkalankatu side. Drilled piling has progressed well, and the majority of the piles have already been installed. Piling, anchoring and excavation works continue in the area, along with finishing works in the bedrock. Bedrock sealing is ongoing, and the structures in the parking facility are largely watertight. Foundation structures are progressing step by step across the area. Next, the sheet pile wall on the Itäinen Pitkäkatu side will be completed.

At the tower building, the removal of the old façade plaster is ongoing, and approximately 85% of the windows have already been replaced. Several work phases are carried out simultaneously in the building, including internal sealing and structural renewal. Rendering works will begin in the next phase.

In the section of the social and health centre under renovation, demolition works continue in phases while structural construction progresses. The work is gradually moving into a stage where new structures are being built in place of the old ones.

Blasting works

The final blasting works in the courtyard area facing Kaskenkatu are currently estimated to take place towards the end of week 20. Blasting and the removal of excavated rock may cause temporary noise and vibration.

Current

The foundation stone laying ceremony for the Kaskia wellbeing block was held at the site on 29 April 2026.

The following works will be initiated next:

  • rendering works at the tower building
  • base filling works in the parking facility


We thank local residents for their patience during the construction works.

04.05.2026 hrs 14:52

Site access

Access to the construction site is strictly prohibited without permission.
Only authorised site personnel may enter the area.
 

Contact

For questions about the project, traffic arrangements, or site updates, please contact:

Managing Director (Eschner Foundation)
Jukka Sjösten
+358 50 352 4906 
jukka.sjosten@eschner.fi

Head of Communications and Grants (Eschner Foundation)
Gunilla Sjöberg
+358 40 515 1537
gunilla.sjoberg@eschner.fi