During week 48, no blasting work will be carried out. The construction site will instead focus on drilling for foundation piles and transporting excavated rock on weekdays from 8:00 to 18:00.
So far, approximately 1,300 m³ of rock has been blasted, out of an estimated total volume of around 4,000 m³.
Blasting work will resume in week 49. We will update the schedule on this website as soon as more information becomes available.
Other work, such as demolition, will continue as usual on the construction site.